πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Pullman Road Wind

Pullman Road Wind is a 300 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2014 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedMay 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
15INR0079
Grid region
ERCOT (Texas)
Developer
SunEdison
Connection point (POI)
79500 Alibates 345kV
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
25 February 2014
Agreement signed
29 May 2014
Proposed online date
October 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem