ONSHORE WIND Β· ERCOT

Zapata Windfarm

Zapata Windfarm is a 251 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
10INR0059
Grid region
ERCOT (Texas)
Developer
Eon Climate & Renewables
Technology
Wind: 251 MW
Total requested
251 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
26 August 2008
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem