ONSHORE WIND Β· ERCOTSpitfire Wind ph 1
Spitfire Wind ph 1 is a 265 MW onshore wind request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 12INR0042a
- Grid region
- ERCOT (Texas)
- Developer
- Clipper Windpower
- Technology
- Wind: 265 MW
- Total requested
- 265 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 25 January 2010
- Proposed online date
- September 2014
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem