ONSHORE WIND Β· ERCOT

Crows Nest Windfarm

Crows Nest Windfarm is a 270 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
07INR0035
Grid region
ERCOT (Texas)
Developer
FPL Energy, LLC
Technology
Wind: 270 MW
Total requested
270 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 March 2006
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem