ONSHORE WIND Β· ERCOTPumpkin Farm Wind
Pumpkin Farm Wind is a 281 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Floyd County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2014 (completed)
- Withdrawn / abandonedMay 2020 (project stopped here)
- ConsentedMar 2017 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 16INR0037c
- Grid region
- ERCOT (Texas)
- Developer
- Apex Clean
- Connection point (POI)
- 79505 White River 345kV
- Location
- Floyd County, Texas
- Technology
- Wind: 281 MW
- Total requested
- 281 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 23 February 2014
- Agreement signed
- 24 March 2017
- Proposed online date
- December 2020
- Withdrawn
- May 2020
Location
Marker shows the centre of Floyd County; the queue data does not give exact sites.
Other requests in Floyd County
- Onshore wind project GEN-2024-042, Floyd CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project GEN-2024-041, Floyd CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project GEN-2014-007, Floyd CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GEN-2008-130, Floyd CountyOnshore wind Β· 300 MW Β· withdrawn
- Solar project GEN-2015-070, Floyd CountySolar Β· 300 MW Β· withdrawn
- Solar project GEN-2018-073, Floyd CountySolar Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2004-004, Floyd CountyOnshore wind Β· 240 MW Β· withdrawn
- Gas project GEN-2012-038, Floyd CountyGas Β· 203 MW Β· withdrawn
- Onshore wind project GEN-2015-033, Floyd CountyOnshore wind Β· 152 MW Β· withdrawn
- Onshore wind project GEN-2014-074, Floyd CountyOnshore wind Β· 152 MW Β· withdrawn
- Onshore wind project GEN-2008-015, Floyd CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2008-014, Floyd CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem