United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2018-073, Floyd County

Solar project GEN-2018-073, Floyd County is a 250 MW solar request withdrawn in the SPP interconnection queue, in Floyd County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2018 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-073
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
345kV Crawfish Substation
Location
Floyd County, Texas
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
24 October 2018
Proposed online date
October 2026
Withdrawn
September 2023

Location

Marker shows the centre of Floyd County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Floyd County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem