πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2015-070, Floyd County

Solar project GEN-2015-070, Floyd County is a 300 MW solar request withdrawn in the SPP interconnection queue, in Floyd County, Texas, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandonedJan 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-070
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Oklaunion-Lawton Eastside 345 kV
Location
Floyd County, Texas
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
9 October 2015
Proposed online date
December 2019
Withdrawn
January 2016

Location

Marker shows the centre of Floyd County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Floyd County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem