๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2018 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown34867.1 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

348 requests ยท page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Chester Solar
Solar
120 MWAgreement signed Chesterfield, VAPJM Dec 2018target 2027
Tracy Solar Energy Center
Solar ยท Tracy Solar Energy Center, LLC
119 MWIn study Jefferson, NYNYISO Oct 2018target 2028
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Reclaimed Wind
Battery storage
114 MWAgreement signed Alameda, CACAISO Apr 2018target 2026
Solar + storage project G0596, Yakima County
Solar + storage
112 MWIn study Yakima, WAWest Jul 2018target 2021
Strawhat Solar Energy Center
Solar
110 MWPaused / redesign Hardin, OHPJM Aug 2018target 2026
Shady Oaks Wind Power Project
Onshore wind
106 MWAgreement signed Lee, ILPJM Mar 2018target 2027
High Bridge Wind
Onshore wind ยท High Bridge Wind, LLC
101 MWIn study Chenango, NYNYISO Apr 2018target 2026
Solar project 55, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Solar project 56, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Battery storage project GEN-2018-024, Muskogee County
Battery storage
100 MWAgreement signed Muskogee, OKSPP May 2018target 2028
Arroyo Solar
Solar + storage ยท BT Cantwell Solar, LLC
100 MWAgreement signed Cameron, TXERCOT May 2018target 2028
Battery storage project GEN-2019-002, Mayes County
Battery storage
100 MWAgreement signed Mayes, OKSPP Nov 2018target 2027
Battery storage project GEN-2018-026, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP May 2018target 2026
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Bear Ridge Solar
Solar ยท Bear Ridge Solar, LLC
100 MWIn study Niagara, NYNYISO Mar 2018target 2027
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Madison County Solar
Solar
100 MWPaused / redesign Madison, INPJM Mar 2018target 2025
Battery storage project GEN-2018-027, Tulsa County
Battery storage
100 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Blue Jay Solar
Solar
100 MWPaused / redesign Pulaski, VAPJM Mar 2018target 2025
Solar project 73, Adams County
Solar
100 MWIn study Adams, WAWest Oct 2018target 2020
Solar project G0586, Klickitat County
Solar
100 MWIn study Klickitat, WAWest Apr 2018target 2022
Solar project J1124, Olmsted County
Solar
100 MWUnder construction Olmsted, MNMISO Mar 2018target 2024
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Bakers Pond Solar
Solar
100 MWPaused / redesign Prince George, VAPJM Sep 2018target 2026
Battery storage project Company 161, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2018target 2021
Solar project J1092, St. Croix County
Solar
100 MWAgreement signed St. Croix, WIMISO Mar 2018target 2023
Solar project J962, Desoto County
Solar
100 MWUnder construction Desoto, MSMISO Mar 20182024
Battery storage project GEN-2018-037, Douglas County
Battery storage
100 MWPaused / redesign Douglas, NESPP May 2018target 2030
Battery storage project GEN-2018-029, Oklahoma County
Battery storage
100 MWAgreement signed Oklahoma, OKSPP May 2018target 2028
Solar project J1131, Scott County
Solar
100 MWUnder construction Scott, IAMISO Mar 2018target 2024
Solar project J1171, Dodge County
Solar
100 MWUnder construction Dodge, WIMISO Mar 20182024
Solar project IA-PNM-2018-03, San Juan County
Solar ยท DESRI Rockmont Development
100 MWPaused / redesign San Juan, NMWest Jul 2018target 2021
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Azalea
Solar + storage
99.3 MWAgreement signed Kern, CACAISO Apr 2018target 2025
Solar project J1144, Covington County
Solar
96.0 MWUnder construction Covington, MSMISO Mar 2018target 2022
Northern Bobwhite Solar
Solar
96.0 MWAgreement signed Marion, KYPJM Sep 2018target 2027
Battery storage project GEN-2018-108, Barber County
Battery storage
95.0 MWAgreement signed Barber, KSSPP Nov 2018target 2028
Solar project 81, Adams County
Solar
94.0 MWIn study Adams, WAWest Dec 2018target 2020
Solar + storage project 1008, Yakima County
Solar + storage ยท Black Rock Solar, LLC
94.0 MWAgreement signed Yakima, WAWest Mar 2018target 2023
Moraine Solar Energy Center
Solar ยท Moraine Solar Energy Center, LLC
93.5 MWIn study Allegany, NYNYISO Jun 2018target 2028
Solano 4 Wind
Onshore wind
92.4 MWAgreement signed Solano, CACAISO Apr 2018target 2025
Chalan Solar
Solar + storage
91.8 MWAgreement signed Kern, CACAISO Apr 2018target 2026
Tyson Nick Solar
Solar ยท Tyson Nick Solar Project, LLC
90.0 MWPaused / redesign Lamar, TXERCOT Dec 20182025
Raleigh Solar Project
Solar
90.0 MWPaused / redesign Raleigh, WVPJM Sep 2018target 2025
Waller Solar I
Solar
86.0 MWAgreement signed Lancaster, VAPJM Mar 2018target 2027
Beaver Creek Solar
Solar
80.3 MWPaused / redesign Franklin, PAPJM Feb 2018target 2024
Solar + storage project 358, Yellowstone County
Solar + storage
80.0 MWPaused / redesign Yellowstone, MTWest Oct 2018target 2022
Solar + storage project TCS-03, Adams County
Solar + storage
80.0 MWPaused / redesign Adams, WAWest Aug 2018
Solar project Company IH, Pershing County
Solar
80.0 MWAgreement signed Pershing, NVWest Mar 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)