ONSHORE WIND · CAISO

Solano 4 Wind

Solano 4 Wind is a 92.4 MW onshore wind request with a signed interconnection agreement in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2018 (completed)
  2. ConsentedFeb 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1463
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Birds Landing 230 kV
Location
Solano County, California
Technology
Wind: 92.4 MW
Total requested
92.4 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
16 April 2018
Agreement signed
27 February 2023
Proposed online date
May 2025

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Solano County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem