Tyson Nick Solar is a 90.0 MW solar request suspended in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Dec 2018 (current stage)
  2. ConsentedAug 2020 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingOct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
20INR0222
Grid region
ERCOT (Texas)
Developer
Tyson Nick Solar Project, LLC
Connection point (POI)
1700 Toco 138kV
Location
Lamar County, Texas
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Study phase
IA
Queue status
Suspended
Entered queue
11 December 2018
Agreement signed
28 August 2020
Proposed online date
October 2025
Came online
October 2025

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem