United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1171, Dodge County

Solar project J1171, Dodge County is a 100 MW solar request under construction in the MISO interconnection queue, in Dodge County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (current stage)
  4. OperatingMar 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1171
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Butternut 138 kV Substation
Location
Dodge County, Wisconsin
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
19 May 2021
Proposed online date
January 2023
Came online
March 2024

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Dodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem