Battery storage project J1345, Dodge County

Battery storage project J1345, Dodge County is a 25.0 MW battery storage request withdrawn in the MISO interconnection queue, in Dodge County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1345
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
North Beaver Dam 69kV Substation
Location
Dodge County, Wisconsin
Technology
Battery: 25.0 MW
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
October 2021
Withdrawn
March 2022

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Dodge County