United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1003, Dodge County
Solar project J1003, Dodge County is a 50.0 MW solar request built and operating in the MISO interconnection queue, in Dodge County, Wisconsin, connecting to American Transmission Co..
Request details
- Queue ID
- J1003
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- North Beaver Dam 69 kV Substation
- Location
- Dodge County, Wisconsin
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 5 May 2021
- Proposed online date
- June 2023
- Came online
- June 2023
Location
Marker shows the centre of Dodge County; the queue data does not give exact sites.
Other requests in Dodge County
- Solar project J1171, Dodge CountySolar · 100 MW · under construction
- Onshore wind project G368, Dodge CountyOnshore wind · 200 MW · built
- Onshore wind project G338, Dodge CountyOnshore wind · 54.0 MW · built
- Other project G306, Dodge CountyOther · 200 MW · withdrawn
- Onshore wind project G485, Dodge CountyOnshore wind · 60.0 MW · withdrawn
- Battery storage project J1345, Dodge CountyBattery storage · 25.0 MW · withdrawn
- Onshore wind project J765, Dodge CountyOnshore wind · 4.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem