🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1003, Dodge County

Solar project J1003, Dodge County is a 50.0 MW solar request built and operating in the MISO interconnection queue, in Dodge County, Wisconsin, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1003
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
North Beaver Dam 69 kV Substation
Location
Dodge County, Wisconsin
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
5 May 2021
Proposed online date
June 2023
Came online
June 2023

Location

Marker shows the centre of Dodge County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Dodge County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem