ONSHORE WIND · MISOOnshore wind project G338, Dodge County
Onshore wind project G338, Dodge County is a 54.0 MW onshore wind request built and operating in the MISO interconnection queue, in Dodge County, Wisconsin.
Request details
- Queue ID
- G338
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Rubicon - Hartford 138kV
- Location
- Dodge County, Wisconsin
- Technology
- Wind: 54.0 MW
- Total requested
- 54.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 23 April 2003
- Agreement signed
- 25 October 2004
- Proposed online date
- October 2003
- Came online
- October 2003
Location
Marker shows the centre of Dodge County; the queue data does not give exact sites.
Other requests in Dodge County
- Solar project J1171, Dodge CountySolar · 100 MW · under construction
- Onshore wind project G368, Dodge CountyOnshore wind · 200 MW · built
- Solar project J1003, Dodge CountySolar · 50.0 MW · built
- Other project G306, Dodge CountyOther · 200 MW · withdrawn
- Onshore wind project G485, Dodge CountyOnshore wind · 60.0 MW · withdrawn
- Battery storage project J1345, Dodge CountyBattery storage · 25.0 MW · withdrawn
- Onshore wind project J765, Dodge CountyOnshore wind · 4.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem