Solar project G0586, Klickitat County

Solar project G0586, Klickitat County is a 100 MW solar request in interconnection study in the West interconnection queue, in Klickitat County, Washington.

Queue statusIn planning
  1. PlanningQueued Apr 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0586
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's Spring Creek 230 kV Substation.
Location
Klickitat County, Washington
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
6 April 2018
Proposed online date
June 2022

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.