United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J1144, Covington County
Solar project J1144, Covington County is a 96.0 MW solar request under construction in the MISO interconnection queue, in Covington County, Mississippi, connecting to COOPERATIVE ENERGY.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedSep 2020 (completed)
- Construction (current stage)
- OperatingTarget Jun 2022 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1144
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- COOPERATIVE ENERGY
- Connection point (POI)
- Moselle - Columbia 161kV Line Tap
- Location
- Covington County, Mississippi
- Technology
- Solar: 96.0 MW
- Total requested
- 96.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 10 September 2020
- Proposed online date
- June 2022
Location
Marker shows the centre of Covington County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Covington County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem