United States › Grid › Interconnection queues › Kansas

BATTERY STORAGE · SPP

Battery storage project GEN-2018-108, Barber County

Battery storage project GEN-2018-108, Barber County is a 95.0 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Barber County, Kansas, connecting to ITCGP.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-108
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Thistle 345kV substation
Location
Barber County, Kansas
Technology
Battery: 95.0 MW
Total requested
95.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
21 November 2018
Proposed online date
December 2028

Location

Marker shows the centre of Barber County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Barber County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem