United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2006-021, Barber County

Onshore wind project GEN-2006-021, Barber County is a 94.0 MW onshore wind request built and operating in the SPP interconnection queue, in Barber County, Kansas, connecting to ITCGP.

Queue statusOperating
  1. PlanningQueued Jun 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2006-021
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Flat Ridge Tap 138kV
Location
Barber County, Kansas
Technology
Wind: 94.0 MW
Total requested
94.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
21 June 2006
Proposed online date
December 2008
Came online
December 2008

Location

Marker shows the centre of Barber County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Barber County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem