United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2012-023, Barber County

Onshore wind project GEN-2012-023, Barber County is a 115 MW onshore wind request withdrawn in the SPP interconnection queue, in Barber County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2012 (completed)
  2. Withdrawn / abandonedAug 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2012-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Viola 345kV
Location
Barber County, Kansas
Technology
Wind: 115 MW
Total requested
115 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
27 September 2012
Proposed online date
December 2014
Withdrawn
August 2014

Location

Marker shows the centre of Barber County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Barber County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem