Solar project GEN-2017-018, Barber County

Solar project GEN-2017-018, Barber County is a 189 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Barber County, Kansas, connecting to ITCGP.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingApr 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-018
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Thistle 345 kV sub
Location
Barber County, Kansas
Technology
Solar: 189 MW
Total requested
189 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 May 2017
Proposed online date
April 2025
Came online
April 2025

Location

Marker shows the centre of Barber County; the queue data does not give exact sites.