ONSHORE WIND Β· SPPOnshore wind project GEN-2011-043, Barber County
Onshore wind project GEN-2011-043, Barber County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Barber County, Kansas, connecting to WERE.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2011 (completed)
- Withdrawn / abandonedJan 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2011-043
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WERE
- Connection point (POI)
- Thistle 345kV
- Location
- Barber County, Kansas
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 28 September 2011
- Proposed online date
- December 2013
- Withdrawn
- January 2014
Location
Marker shows the centre of Barber County; the queue data does not give exact sites.
Other requests in Barber County
- Solar project GEN-2017-018, Barber CountySolar Β· 189 MW Β· agreement signed
- Battery storage project GEN-2018-108, Barber CountyBattery storage Β· 95.0 MW Β· agreement signed
- Onshore wind project GEN-2007-025, Barber CountyOnshore wind Β· 299 MW Β· built
- Onshore wind project GEN-2006-021, Barber CountyOnshore wind Β· 94.0 MW Β· built
- Onshore wind project GEN-2008-076, Barber CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2008-074, Barber CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2008-073, Barber CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2008-075, Barber CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2011-042, Barber CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2011-041, Barber CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2011-044, Barber CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2012-023, Barber CountyOnshore wind Β· 115 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem