United States › Grid › Interconnection queues › Mississippi

SOLAR · MISO

Solar project J962, Desoto County

Solar project J962, Desoto County is a 100 MW solar request under construction in the MISO interconnection queue, in Desoto County, Mississippi, connecting to ENTERGY MISSISSIPPI.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedAug 2020 (completed)
  3. Construction (current stage)
  4. OperatingJun 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J962
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI
Connection point (POI)
Twinkletown 230 kV Substation
Location
Desoto County, Mississippi
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
12 March 2018
Agreement signed
12 August 2020
Proposed online date
June 2022
Came online
June 2024

Location

Marker shows the centre of Desoto County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Desoto County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem