United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,158262.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,158 requests · page 5 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Lumina Solar
Solar · IP Lumina, LLC
313 MWWithdrawn / abandoned Scurry, TXERCOT Sep 2018target 2022
Fletcher BESS
Battery storage · Archer Energy Center, LLC
310 MWWithdrawn / abandoned ERCOT Jul 2024target 2027
Barbers Hill BESS
Battery storage · Black Mountain Energy Storage II
308 MWWithdrawn / abandoned ERCOT Jan 2023target 2027
Easter Wind
Onshore wind · TriGlobal
308 MWWithdrawn / abandoned Castro, TXERCOT Dec 2013target 2021
Valhalla Solar
Solar · Industrial Papa Project LLC
307 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2023target 2026
Box Canyon Energy Storage
Other · Box Canyon Energy Storage Project, LLC
306 MWWithdrawn / abandoned Callahan, TXERCOT Jan 2024target 2027
Goose Foot Energy Storage
Battery storage · Goose Foot Energy Storage Project, LLC
306 MWWithdrawn / abandoned ERCOT Dec 2024target 2028
Tyler BESS
Battery storage · SMT Tyler LLC
305 MWWithdrawn / abandoned ERCOT Jul 2023target 2027
Frio Flat Wind
Onshore wind · Phoenix Wind, LLC
305 MWWithdrawn / abandoned Deaf Smith, TXERCOT Jun 2019target 2022
Voyager Solar
Solar · EDF Renewables Development, Inc.
304 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2019target 2025
BRP Parana BESS
Battery storage · BRP Parana BESS
304 MWWithdrawn / abandoned ERCOT May 2021target 2028
Amethyst Storage
Other · Riggs Energy Storage LLC
304 MWWithdrawn / abandoned Kaufman, TXERCOT Aug 2021target 2023
Wildrose Wind
Onshore wind · S Power
303 MWWithdrawn / abandoned Swisher, TXERCOT Apr 2011target 2021
Great Dane Wind
Onshore wind · Seventus
303 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2018target 2020
Stump Tail BESS
Other · Moccasin Pointe Grid, LLC
302 MWWithdrawn / abandoned Harris, TXERCOT Apr 2021target 2028
Soleil Storage
Battery storage · Soleil Solar, LLC
302 MWWithdrawn / abandoned Clay, TXERCOT Sep 2022target 2027
Mariette Solar
Solar · Mariette Solar LLC
301 MWWithdrawn / abandoned Wichita, TXERCOT Oct 2024target 2028
Fox Run Energy Storage
Other · Fox Run Energy Project, LLC
301 MWWithdrawn / abandoned Jones, TXERCOT Feb 2023target 2026
Pease River Wind
Onshore wind · Eon
301 MWWithdrawn / abandoned Hardeman, TXERCOT Jul 2017target 2021
BRP Pobeda BESS
Battery storage · BRP Pobeda BESS LLC
301 MWWithdrawn / abandoned ERCOT Nov 2020target 2028
Harden BESS
Battery storage · BRP Blue Topaz 14, LLC
301 MWWithdrawn / abandoned ERCOT Jul 2023target 2025
Blossomheath BESS
Battery storage · Taurbeng LLC
301 MWWithdrawn / abandoned Ellis, TXERCOT May 2023target 2026
Brazoria Texas Peakers
Gas · LS Power Associates, LP
300 MWWithdrawn / abandoned ERCOT Aug 2008target 2050
Blanco Canyon Wind
Onshore wind · Blanco Canyon Wind Development
300 MWWithdrawn / abandoned ERCOT Jul 2011target 2050
Galveston Offshore Wind
Offshore wind · Galveston - Offshore Wind, LLC
300 MWWithdrawn / abandoned ERCOT Jan 2007
Lazarus Solar
Solar · Lendlease Energy Development
300 MWWithdrawn / abandoned Swisher, TXERCOT Dec 2019target 2022
Route66 Wind
Onshore wind · Route 66 LLC
300 MWWithdrawn / abandoned ERCOT Jul 2012target 2015
McAdoo Project
Onshore wind · Invenergy Wind
300 MWWithdrawn / abandoned ERCOT May 2006target 2008
Fort McKavett Wind
Onshore wind · Nextera
300 MWWithdrawn / abandoned Menard, TXERCOT Aug 2018target 2020
Plateau Solar
Solar · Innovative Solar 206, LLC
300 MWWithdrawn / abandoned ERCOT Dec 2019target 2025
Stone Ranch Wind
Onshore wind · Iberdrola Renewables
300 MWWithdrawn / abandoned ERCOT Jul 2008target 2050
Lazy J Solar
Solar · ConnectGen Operating LLC
300 MWWithdrawn / abandoned Leon, TXERCOT Jul 2019target 2021
MykawaAlta
Gas · Alta Power LLC
300 MWWithdrawn / abandoned Harris, TXERCOT Aug 2019target 2021
Nacogdoches CC Generating Facility
Gas · Nacogdoches Power, LLC
300 MWWithdrawn / abandoned ERCOT Dec 2006
Windwood Wind
Onshore wind · Lincoln Clean
300 MWWithdrawn / abandoned ERCOT Jun 2012target 2018
Reed Road Project
Gas · LS Power Associates, LP
300 MWWithdrawn / abandoned ERCOT Nov 2008target 2050
Tiger Wind
Onshore wind · Nextera
300 MWWithdrawn / abandoned Taylor, TXERCOT Oct 2018target 2022
Pistol Hill Energy Center
Onshore wind · Invenergy
300 MWWithdrawn / abandoned ERCOT Aug 2006target 2050
Karankawa Wind Farm
Onshore wind · Acciona Wind Energy USA, LLC
300 MWWithdrawn / abandoned ERCOT Apr 2008target 2050
Saturn 1 Wind
Onshore wind · Saturn 1 wind
300 MWWithdrawn / abandoned Zapata, TXERCOT Jul 2019target 2022
Callisto
Solar · Intersect Power
300 MWWithdrawn / abandoned Borden, TXERCOT Apr 2018target 2021
Welder Solar
Solar · Welder Solar, LLC
300 MWWithdrawn / abandoned Bee, TXERCOT Jun 2019target 2024
Comanche Mesa
Onshore wind · Pioneer Green Energy, LLC
300 MWWithdrawn / abandoned ERCOT Mar 2011target 2050
Zapata I W
Onshore wind · Nextera
300 MWWithdrawn / abandoned Jim Hogg, TXERCOT Apr 2015target 2019
Sterling Energy Center
Onshore wind · Invenergy
300 MWWithdrawn / abandoned ERCOT Feb 2007target 2050
AltaRanch
Gas · Alta Power LLC
300 MWWithdrawn / abandoned Harris, TXERCOT Aug 2019target 2021
Milky Way Solar
Solar · Aurora Solar LLC
300 MWWithdrawn / abandoned Robertson, TXERCOT Apr 2021target 2025
Huckabay Hills Windfarm
Onshore wind · FPL Energy, LLC
300 MWWithdrawn / abandoned ERCOT Sep 2008target 2050
Mitchell I Windpark 1
Onshore wind · Redbank, LLC
300 MWWithdrawn / abandoned ERCOT Apr 2007target 2050
Pradera Solar
Solar · Pradera Solar, LLC
300 MWWithdrawn / abandoned Webb, TXERCOT Oct 2019target 2022
Page 5 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)