πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OFFSHORE WIND Β· ERCOT

Galveston Offshore Wind

Galveston Offshore Wind is a 300 MW offshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
09INR0022
Grid region
ERCOT (Texas)
Developer
Galveston - Offshore Wind, LLC
Technology
Offshore Wind: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
2 January 2007

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem