SOLAR Β· ERCOT

Callisto

Callisto is a 300 MW solar request withdrawn in the ERCOT interconnection queue, in Borden County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0009
Grid region
ERCOT (Texas)
Developer
Intersect Power
Connection point (POI)
59900 Long Draw 345kV
Location
Borden County, Texas
Technology
Solar: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
11 April 2018
Proposed online date
December 2021
Withdrawn
January 2019

Location

Marker shows the centre of Borden County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Borden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem