United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Tumbleweed Solar

Tumbleweed Solar is a 614 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Borden County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0086
Grid region
ERCOT (Texas)
Developer
Hecate Energy Tumbleweed Solar LLC
Connection point (POI)
59905 Faraday 345 kV
Location
Borden County, Texas
Technology
Solar: 614 MW · Battery
Total requested
614 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 September 2023
Proposed online date
December 2027

Location

Marker shows the centre of Borden County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Borden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem