BATTERY STORAGE · ERCOTIron Belt Energy Storage
Iron Belt Energy Storage is a 402 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Borden County, Texas.
Queue statusConsented
- PlanningQueued Jan 2023 (completed)
- ConsentedJan 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0208
- Grid region
- ERCOT (Texas)
- Developer
- Iron Belt Energy Storage Project, LLC
- Connection point (POI)
- Long Draw (# 59900) - Volta (#59910) 345kV
- Location
- Borden County, Texas
- Technology
- Battery: 402 MW
- Total requested
- 402 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 3 January 2023
- Agreement signed
- 16 January 2023
- Proposed online date
- July 2027
Location
Marker shows the centre of Borden County; the queue data does not give exact sites.
Other requests in Borden County
- Magnet SolarSolar + storage · 503 MW · agreement signed
- Lyra SolarSolar + storage · 500 MW · agreement signed
- Antila SolarSolar · 500 MW · agreement signed
- Lyra StorageSolar + storage · 500 MW · agreement signed
- Juno 3 SolarSolar · 500 MW · agreement signed
- Uva Creek SolarSolar · 302 MW · agreement signed
- Tumbleweed SolarSolar + storage · 614 MW · in study
- Tumbleweed StorageSolar + storage · 507 MW · in study
- Draco SolarSolar · 500 MW · in study
- Magnet StorageSolar + storage · 427 MW · in study
- Gail Mountain SolarSolar · 244 MW · in study
- Caesar StorageSolar + storage · 206 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem