Magnet Storage

Magnet Storage is a 427 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Borden County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0298
Grid region
ERCOT (Texas)
Developer
HyFuels Big Spring LLC
Connection point (POI)
Faraday 345 kV Substation (#59905)
Location
Borden County, Texas
Technology
Battery: 427 MW · Battery
Total requested
427 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 July 2025
Proposed online date
July 2029

Location

Marker shows the centre of Borden County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Borden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem