SOLAR Β· ERCOT

Welder Solar

Welder Solar is a 300 MW solar request withdrawn in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2019 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0356
Grid region
ERCOT (Texas)
Developer
Welder Solar, LLC
Connection point (POI)
tap 345kV 8624 Grissom - 8455 Lon Hill
Location
Bee County, Texas
Technology
Solar: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
17 June 2019
Proposed online date
October 2024
Withdrawn
March 2024

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem