πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Saturn 1 Wind

Saturn 1 Wind is a 300 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Zapata County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2019 (completed)
  2. Withdrawn / abandonedSep 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0289
Grid region
ERCOT (Texas)
Developer
Saturn 1 wind
Connection point (POI)
80220 Cenizo 345kV
Location
Zapata County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
18 July 2019
Proposed online date
December 2022
Withdrawn
September 2020

Location

Marker shows the centre of Zapata County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Zapata County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem