SOLAR Β· ERCOT

Pradera Solar

Pradera Solar is a 300 MW solar request withdrawn in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedSep 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0247
Grid region
ERCOT (Texas)
Developer
Pradera Solar, LLC
Connection point (POI)
80219 Lobo 345kV
Location
Webb County, Texas
Technology
Solar: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 October 2019
Proposed online date
December 2022
Withdrawn
September 2020

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Webb County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem