United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Voyager Solar

Voyager Solar is a 304 MW solar request withdrawn in the ERCOT interconnection queue, in Wharton County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2019 (completed)
  2. Withdrawn / abandonedJun 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0237
Grid region
ERCOT (Texas)
Developer
EDF Renewables Development, Inc.
Connection point (POI)
44200 Hillje 345kV
Location
Wharton County, Texas
Technology
Solar: 304 MW
Total requested
304 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
3 January 2019
Proposed online date
December 2025
Withdrawn
June 2024

Location

Marker shows the centre of Wharton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Wharton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem