BATTERY STORAGE · ERCOT

Toce BESS 1

Toce BESS 1 is a 205 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2023 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0293
Grid region
ERCOT (Texas)
Developer
TOCE BESS 1, LLC
Connection point (POI)
138 kV Danevang Switching Station (Bus# 5546)
Location
Wharton County, Texas
Technology
Battery: 205 MW
Total requested
205 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
13 October 2023
Agreement signed
30 December 2024
Proposed online date
June 2027

Location

Marker shows the centre of Wharton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wharton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem