SOLAR · ERCOTSbranch Solar
Sbranch Solar is a 234 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.
Queue statusConsented
- PlanningQueued Jan 2019 (completed)
- ConsentedJul 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 22INR0205
- Grid region
- ERCOT (Texas)
- Developer
- Bernard Creek Solar, LLC
- Connection point (POI)
- Tap 138kV 44190 East Bernard - 44130 Caney
- Location
- Wharton County, Texas
- Technology
- Solar: 234 MW
- Total requested
- 234 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 3 January 2019
- Agreement signed
- 26 July 2020
- Proposed online date
- March 2026
Location
Marker shows the centre of Wharton County; the queue data does not give exact sites.
Other requests in Wharton County
- Danish Fields SolarSolar · 603 MW · agreement signed
- Space City SolarSolar · 366 MW · agreement signed
- OCI SunRoperSolar · 265 MW · agreement signed
- Maleza SolarSolar + storage · 255 MW · agreement signed
- Photon Solar 1 2 SLFSolar · 236 MW · agreement signed
- Sorghum BESSBattery storage · 209 MW · agreement signed
- Toce BESS 1Battery storage · 205 MW · agreement signed
- Erin SolarSolar · 203 MW · agreement signed
- Ramsey StorageBattery storage · 201 MW · agreement signed
- Lane City WindOnshore wind · 200 MW · agreement signed
- Northington SolarSolar · 130 MW · agreement signed
- Photon Solar 3 SLFSolar · 110 MW · agreement signed