Sbranch Solar

Sbranch Solar is a 234 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2019 (completed)
  2. ConsentedJul 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0205
Grid region
ERCOT (Texas)
Developer
Bernard Creek Solar, LLC
Connection point (POI)
Tap 138kV 44190 East Bernard - 44130 Caney
Location
Wharton County, Texas
Technology
Solar: 234 MW
Total requested
234 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
3 January 2019
Agreement signed
26 July 2020
Proposed online date
March 2026

Location

Marker shows the centre of Wharton County; the queue data does not give exact sites.