BATTERY STORAGE · ERCOTRamsey Storage
Ramsey Storage is a 201 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.
Queue statusConsented
- PlanningQueued May 2020 (completed)
- ConsentedAug 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 21INR0505
- Grid region
- ERCOT (Texas)
- Developer
- Hecate Energy Ramsey Storage LLC
- Connection point (POI)
- 44200 Hillje 345kV
- Location
- Wharton County, Texas
- Technology
- Battery: 201 MW
- Total requested
- 201 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 20 May 2020
- Agreement signed
- 11 August 2022
- Proposed online date
- December 2027
Location
Marker shows the centre of Wharton County; the queue data does not give exact sites.
Other requests in Wharton County
- Danish Fields SolarSolar · 603 MW · agreement signed
- Space City SolarSolar · 366 MW · agreement signed
- OCI SunRoperSolar · 265 MW · agreement signed
- Maleza SolarSolar + storage · 255 MW · agreement signed
- Photon Solar 1 2 SLFSolar · 236 MW · agreement signed
- Sbranch SolarSolar · 234 MW · agreement signed
- Sorghum BESSBattery storage · 209 MW · agreement signed
- Toce BESS 1Battery storage · 205 MW · agreement signed
- Erin SolarSolar · 203 MW · agreement signed
- Lane City WindOnshore wind · 200 MW · agreement signed
- Northington SolarSolar · 130 MW · agreement signed
- Photon Solar 3 SLFSolar · 110 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem