United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Maleza Solar

Maleza Solar is a 255 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2018 (completed)
  2. ConsentedJan 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0220
Grid region
ERCOT (Texas)
Developer
Brush Solar LLC
Connection point (POI)
tap Blue – Hillje 345 kv Ckt.#27
Location
Wharton County, Texas
Technology
Solar: 255 MW · Battery
Total requested
255 MW
Study phase
SS Completed, FIS Not Started, IA
Queue status
Active
Entered queue
6 December 2018
Agreement signed
27 January 2021
Proposed online date
February 2027

Location

Marker shows the centre of Wharton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wharton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem