United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Photon Solar 1 2 SLF

Photon Solar 1 2 SLF is a 236 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Wharton County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0493
Grid region
ERCOT (Texas)
Developer
GulfStar Power, LLC
Connection point (POI)
44880 Waterh_POI_5 345kV
Location
Wharton County, Texas
Technology
Solar: 236 MW
Total requested
236 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 September 2024
Proposed online date
February 2026

Location

Marker shows the centre of Wharton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wharton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem