United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTMilky Way Solar
Milky Way Solar is a 300 MW solar request withdrawn in the ERCOT interconnection queue, in Robertson County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandonedJun 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0046
- Grid region
- ERCOT (Texas)
- Developer
- Aurora Solar LLC
- Connection point (POI)
- 967 Gibbons Creek - 3400 Twin Oak 345 kV transmission line.
- Location
- Robertson County, Texas
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 12 April 2021
- Proposed online date
- December 2025
- Withdrawn
- June 2022
Location
Marker shows the centre of Robertson County; the queue data does not give exact sites.
Other requests in Robertson County
- Big Rooter East SolarSolar + storage Β· 555 MW Β· agreement signed
- Big Rooter West SolarSolar + storage Β· 403 MW Β· agreement signed
- Barton Branch IABattery storage Β· 204 MW Β· agreement signed
- Tidwell Prairie II BattBattery storage Β· 204 MW Β· agreement signed
- Big Rooter East StorageSolar + storage Β· 201 MW Β· agreement signed
- Camp Creek Solar SLFSolar + storage Β· 110 MW Β· agreement signed
- BRP Mekong BESSBattery storage Β· 410 MW Β· in study
- Buffalo Prairie StorageSolar + storage Β· 308 MW Β· in study
- Buffalo Meadow SolarSolar + storage Β· 251 MW Β· in study
- Bee Branch IABattery storage Β· 203 MW Β· in study
- Big Rooter West StorageSolar + storage Β· 201 MW Β· in study
- Prairie Horizon Energy Storage 4Battery storage Β· 102 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem