MykawaAlta

MykawaAlta is a 300 MW gas request withdrawn in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedJun 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0398
Grid region
ERCOT (Texas)
Developer
Alta Power LLC
Connection point (POI)
tap 138kV 42741 Gulfgate - 43052 Pearland
Location
Harris County, Texas
Technology
Gas: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
12 August 2019
Proposed online date
November 2021
Withdrawn
June 2021

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Harris County