United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Route66 Wind

Route66 Wind is a 300 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0032b
Grid region
ERCOT (Texas)
Developer
Route 66 LLC
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
24 July 2012
Proposed online date
December 2015

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem