BATTERY STORAGE Β· ERCOT

Tyler BESS

Tyler BESS is a 305 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0471
Grid region
ERCOT (Texas)
Developer
SMT Tyler LLC
Connection point (POI)
3104 Shamburger Switch 138kV
Technology
Battery: 305 MW
Total requested
305 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
10 July 2023
Proposed online date
June 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem