United States › Grid › Interconnection queues › Michigan

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Michigan — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30558.6 GW
Active in queue58.6 GW305 requests
Agreement signed4,949 MW37 requests
Withdrawn39070.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

305 requests · page 4 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2378, Macomb County
Battery storage
152 MWIn study Macomb, MIMISO Sep 2022target 2026
Solar project J3682, Muskegon County
Solar
150 MWIn study Muskegon, MIMISO Apr 2024target 2028
Solar project J3471, Branch County
Solar
150 MWIn study Branch, MIMISO Apr 2024target 2028
Solar project J3844, St. Joseph County
Solar
150 MWIn study St. Joseph, MIMISO Nov 2024target 2029
Solar project J2678, Delta County
Solar
150 MWIn study Delta, MIMISO Sep 2022target 2025
Battery storage project J3651, Lenawee County
Battery storage
150 MWIn study Lenawee, MIMISO Apr 2024target 2028
Solar project J1553, Clinton County
Solar
150 MWAgreement signed Clinton, MIMISO Dec 2021target 2025
Solar + storage project J2129, Barry County
Solar + storage
150 MWIn study Barry, MIMISO Aug 2021target 2024
Battery storage project J3636, Tuscola County
Battery storage
150 MWIn study Tuscola, MIMISO Apr 2024target 2028
Solar project J875, Lenawee County
Solar
150 MWUnder construction Lenawee, MIMISO Jun 2017target 2022
Solar project J2875, Presque Isle County
Solar
150 MWIn study Presque Isle, MIMISO Sep 2022target 2025
Solar project J3473, Bay County
Solar
150 MWIn study Bay, MIMISO Apr 2024target 2028
Battery storage project J3650, Genesee County
Battery storage
150 MWIn study Genesee, MIMISO Apr 2024target 2028
Wingstem Solar Energy Farm
Solar
150 MWPaused / redesign Cass, MIPJM Sep 2018target 2025
Battery storage project AI1-166, Cass County
Battery storage
150 MWIn study Cass, MIPJM Sep 2022target 2028
Solar + storage project AH2-149, Van Buren County
Solar + storage
150 MWIn study Van Buren, MIPJM Feb 2022target 2026
Surplus; J1062
Other
150 MWIn study Washtenaw, MIMISO Oct 2024target 2027
Solar project J3134, Otsego County
Solar
150 MWIn study Otsego, MIMISO Sep 2022target 2025
Onshore wind project J3645, Huron County
Onshore wind
150 MWIn study Huron, MIMISO Apr 2024target 2028
Solar project J3419, Huron County
Solar
150 MWIn study Huron, MIMISO Mar 2024target 2028
Battery storage project J3776, Midland County
Battery storage
150 MWIn study Midland, MIMISO Apr 2024target 2028
Solar project J1914, Presque Isle County
Solar
150 MWIn study Presque Isle, MIMISO Oct 2023target 2026
Surplus; J875
Other
150 MWIn study Lenawee, MIMISO Oct 2024target 2027
Battery storage project J4122, Shiawassee County
Battery storage
150 MWIn study Shiawassee, MIMISO Sep 2025target 2030
Solar project J4061, Lenawee County
Solar
150 MWIn study Lenawee, MIMISO Aug 2025target 2028
Battery storage project J3009, Washtenaw County
Battery storage
150 MWIn study Washtenaw, MIMISO Aug 2022target 2025
Solar project J3644, Bay County
Solar
150 MWIn study Bay, MIMISO Apr 2024target 2028
Battery storage project J2454, Montcalm County
Battery storage
150 MWIn study Montcalm, MIMISO Sep 2022target 2025
Solar project J3722, Hillsdale County
Solar
150 MWIn study Hillsdale, MIMISO Mar 2024target 2028
Gemstone Solar
Solar
150 MWAgreement signed Cass, MIPJM Jan 2020target 2028
Battery storage project J2589, Jackson County
Battery storage
150 MWIn study Jackson, MIMISO Sep 2022target 2025
Battery storage project J3654, Washtenaw County
Battery storage
150 MWIn study Washtenaw, MIMISO Apr 2024target 2028
Surplus; J1320
Other
150 MWIn study Branch, MIMISO Aug 2024target 2026
Solar project J1320, Branch County
Solar
150 MWAgreement signed Branch, MIMISO Apr 2019target 2025
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Surplus; J806
Other
149 MWIn study Calhoun, MIMISO target 2026
Onshore wind project J4054, Saginaw County
Onshore wind
146 MWIn study Saginaw, MIMISO Sep 2025target 2030
Solar project J3761, Ogemaw County
Solar
146 MWIn study Ogemaw, MIMISO Apr 2024target 2027
Solar project J2669, Mason County
Solar
140 MWIn study Mason, MIMISO Sep 2022target 2025
Solar project J2815, Calhoun County
Solar
140 MWIn study Calhoun, MIMISO Aug 2022target 2026
Solar + storage project J2619, Montcalm County
Solar + storage
140 MWIn study Montcalm, MIMISO Sep 2022target 2026
Solar project J2812, Hillsdale County
Solar
140 MWIn study Hillsdale, MIMISO Sep 2022target 2026
Solar project J3283, Grand Traverse County
Solar
135 MWIn study Grand Traverse, MIMISO Apr 2024target 2028
Solar project J1918, Montcalm County
Solar
132 MWIn study Montcalm, MIMISO Aug 2021target 2026
Solar project J3835, Saginaw County
Solar
130 MWIn study Saginaw, MIMISO Jul 2024target 2028
Solar project J1939, Saginaw County
Solar
125 MWIn study Saginaw, MIMISO Oct 2023target 2023
Solar project J1203, Genesee County
Solar
125 MWUnder construction Genesee, MIMISO Apr 2019target 2025
Solar project J2490, Tuscola County
Solar
125 MWIn study Tuscola, MIMISO Sep 2022target 2025
Solar project J1310, Jackson County
Solar
125 MWUnder construction Jackson, MIMISO Apr 2019target 2024
Solar project J857, Calhoun County
Solar
125 MWUnder construction Calhoun, MIMISO Jun 2017target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)