BATTERY STORAGE · MISO

Battery storage project J2589, Jackson County

Battery storage project J2589, Jackson County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Jackson County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2589
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
TOMPKINS - VROOMAN 138.0kV
Location
Jackson County, Michigan
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
April 2025

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Jackson County