United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J2815, Calhoun County

Solar project J2815, Calhoun County is a 140 MW solar request in interconnection study in the MISO interconnection queue, in Calhoun County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2022 (current stage)
  2. ConsentedAug 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2815
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
ARGENTA - VERONA 138.0kV
Location
Calhoun County, Michigan
Technology
Solar: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
30 August 2022
Agreement signed
21 August 2025
Proposed online date
February 2026

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Calhoun County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem