Solar project J758, Calhoun County

Solar project J758, Calhoun County is a 200 MW solar request built and operating in the MISO interconnection queue, in Calhoun County, Michigan, connecting to METC.

Queue statusOperating
  1. PlanningQueued Nov 2016 (completed)
  2. ConsentedOct 2019 (completed)
  3. Construction (completed)
  4. OperatingApr 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J758
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Verona-Foundry 138kV
Location
Calhoun County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
14 November 2016
Agreement signed
25 October 2019
Proposed online date
April 2022
Came online
April 2022

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.