United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas — page 23
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Easy Battery Energy Storage Center Wind + storage · Easy Wind Energy Center, LLC |
200 MW | In study |
| Borderland ESC Battery storage · FRESH AIR ENERGY II, LLC |
200 MW | In study |
| Rodeo Solar Solar · Core Solar SPV I, LLC |
200 MW | Agreement signed |
| Anson Solar Center, Phase III Solar · Anson Solar Center 3, LLC |
200 MW | In study |
| Millers Branch Solar I Solar · Miller's Branch Solar, LLC |
200 MW | Agreement signed |
| Rattlesnake Gap Wind SLF Onshore wind · ET Fuels US Inc. |
200 MW | In study |
| Armadillo Solar Solar · Armadillo Solar Center, LLC |
200 MW | Agreement signed |
| Battery storage project GEN-2021-038, Titus County Battery storage |
200 MW | In study |
| Biggs BESS Solar + storage · Biggs Battery Facility, LLC |
200 MW | In study |
| Kresge Land Battery Storage Battery storage · Kresge Land Battery Storage LLC |
200 MW | In study |
| Monument Hill Solar Solar · RWE Solar Development, LLC |
200 MW | In study |
| Tierra Blanca W Onshore wind · RWE Renewables Development, LLC |
200 MW | Paused / redesign |
| Lane City Wind Onshore wind · RWE Clean Energy, LLC |
200 MW | Agreement signed |
| Monte Alto 2 Wind Onshore wind · Terra-Gen |
200 MW | Agreement signed |
| Battery storage project GEN-2024-355, Lubbock County Battery storage |
199 MW | In study |
| Wi-Al2-199SB Solar + storage |
199 MW | In study |
| Wi-Al3-199SB Solar + storage |
199 MW | In study |
| Wi-Al-199SB Solar + storage |
199 MW | In study |
| Battery storage project GEN-2024-178, Harrison County Battery storage |
199 MW | In study |
| Pasture Rose Wind Onshore wind · Pasture Rose, LLC |
199 MW | In study |
| Percy Farm Solar Solar · Percy Farm Solar 1, LLC |
199 MW | In study |
| Solar project J2071, Hardin County Solar |
198 MW | In study |
| Cascabel Wind 2 Onshore wind · Vaquero Wind Energy, LLC |
198 MW | Agreement signed |
| Barrosos Creek Wind 3 Onshore wind · Cascabel Wind Energy, LLC |
198 MW | In study |
| Cascabel Wind 1 Onshore wind · Vaquero Wind Energy, LLC |
198 MW | Agreement signed |
| Barrosos Creek Wind 4 Onshore wind · Cascabel Wind Energy, LLC |
198 MW | In study |
| Wood Fern Wind Onshore wind · Wood Fern Wind LLC |
197 MW | In study |
| Loma Pinta Wind Onshore wind · Enerverse |
197 MW | Agreement signed |
| Camino Santiago Solar Solar · Camino Solar Project, LLC |
196 MW | Agreement signed |
| Corralitos Wind 3 Onshore wind · Las Crestas Wind Energy, LLC |
196 MW | In study |
| Corralitos Wind 1 Onshore wind · Vaquero Wind Energy, LLC |
196 MW | Agreement signed |
| Onshore wind project GEN-2018-089, Castro County Onshore wind |
196 MW | Agreement signed |
| Johnson Grass Solar Solar · Johnson Grass Solar ,LLC |
196 MW | In study |
| Wolf Spring Solar Solar + storage · Wolf Spring Solar, LLC |
196 MW | Agreement signed |
| Corralitos Wind 4 Onshore wind · Las Crestas Wind Energy, LLC |
195 MW | In study |
| Corralitos Wind 2 Onshore wind · Vaquero Wind Energy, LLC |
195 MW | Agreement signed |
| Tres Bahias Solar Solar · Tres Bahias Solar Power LLC |
195 MW | Agreement signed |
| Paloma Energy Center Solar + storage · Harrison Street Development, LLC |
194 MW | In study |
| Steelhead Energy Storage Battery storage · GRS BESS TEXAS SEVEN, LLC |
192 MW | In study |
| Argenta Storage Solar + storage · Charter Oak Storage, LLC |
192 MW | Agreement signed |
| Malachite BESS Solar + storage · Malachite Storage LLC |
191 MW | In study |
| Pecos Wind Wind + storage · Midnight Energy Center, LLC |
191 MW | In study |
| Accalia Point Solar Solar · Accalia Point Solar LLC |
191 MW | In study |
| Bullring Wind 3 Onshore wind · Halcon Wind, LLC |
190 MW | Agreement signed |
| Harryoung Solar Solar + storage · Gransolar Texas Four LLC |
190 MW | In study |
| HarryoungBESS Solar + storage · Gransolar Texas Four LLC |
190 MW | In study |
| Crowded Star Solar II Solar + storage · Jones City Solar II, LLC |
190 MW | Agreement signed |
| Chacon Creek Battery storage · Cattlemen BESS LLC |
189 MW | In study |
| Blanket Ranch North Solar Solar + storage · Blanket Ranch North Solar, LLC |
189 MW | In study |
| Timmerman Power Plant Phase 2 Gas · Lower Colorado River Authority |
188 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,976 · 447.2 GW
- SPP (Southwest Power Pool)79 · 20.6 GW
- MISO (Midcontinent)27 · 6,659 MW
- West (non-ISO utilities)12 · 1,947 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)