SOLAR + STORAGE · ERCOT

Harryoung Solar

Harryoung Solar is a 190 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0270
Grid region
ERCOT (Texas)
Developer
Gransolar Texas Four LLC
Connection point (POI)
Tap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV
Location
Cameron County, Texas
Technology
Solar: 190 MW · Battery
Total requested
190 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
23 November 2022
Proposed online date
May 2028

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County