United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Resaca Oasis Storage

Resaca Oasis Storage is a 201 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2024 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0399
Grid region
ERCOT (Texas)
Developer
Resaca Oasis Storage, LLC
Connection point (POI)
# 79601 Stillman Substation 138 kV
Location
Cameron County, Texas
Technology
Battery: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
12 December 2024
Agreement signed
22 May 2025
Proposed online date
September 2027

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem