Wi-Al-199SB is a 199 MW solar + storage request in interconnection study in the West interconnection queue, in El Paso County, Texas, connecting to El Paso Electric Company.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q25-LG-6-10-2
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Alamo 115 kV Substation
Location
El Paso County, Texas
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
10 June 2025
Proposed online date
September 2028

Location

Marker shows the centre of El Paso County; the queue data does not give exact sites.