🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · WEST

Ea150B

Ea150B is a 150 MW battery storage request in interconnection study in the West interconnection queue, in El Paso County, Texas, connecting to El Paso Electric Company.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q25-LG-6-4
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Eastlake 115 kV Substation
Location
El Paso County, Texas
Technology
Battery: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
4 June 2025
Proposed online date
October 2028

Location

Marker shows the centre of El Paso County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in El Paso County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem